Thursday, August 30, 2012

Busy couple of weeks!

This week the majority of our roof was installed.
The plumbers finished their in-wall work and passed the city's inspection.
The a/c work is complete and passed the city's inspection.
Electricians and the low-voltage wiring is being installed.
Brick is ordered. The stone for the front of the house is ordered.
We met with the cabinet maker to start plans.
Most of the windows have been installed. We are waiting on a few casement windows still.
We also met with 2 pool companies. That one is up in the air but we are hoping we can do a pool before we move in also.


The boys all started school and preschool. It has been quite the busy few weeks of life!!

Tuesday, August 21, 2012

Lots of work

There has been lots of progress on the house. The plumbers are almost finished with all the stuff that goes in the walls. All 3 bathtubs are sitting in the dining room.
The electricians marked where all the plugs and lights are going. They will install next week.
The A/C units and duct work will be installed tomorrow.
Roof will be installed soon.
We meet with the cabinet maker tomorrow to start that design process.
All but 3 Windows are in and those should arrive next week.
Once windows are installed and roof is on, we will start install of Sheetrock.
Most of the progress this week is hard to show in pics. But trust me, it's coming right along!