Tuesday, August 21, 2012

Lots of work

There has been lots of progress on the house. The plumbers are almost finished with all the stuff that goes in the walls. All 3 bathtubs are sitting in the dining room.
The electricians marked where all the plugs and lights are going. They will install next week.
The A/C units and duct work will be installed tomorrow.
Roof will be installed soon.
We meet with the cabinet maker tomorrow to start that design process.
All but 3 Windows are in and those should arrive next week.
Once windows are installed and roof is on, we will start install of Sheetrock.
Most of the progress this week is hard to show in pics. But trust me, it's coming right along!

No comments:

Post a Comment